Multimillion-dollar bill to replace Outback power line

Outback residents fear for their community’s future now a 240-kilometre-long power line has reached the “end of its service life”.

Nov 26, 2026, updated Nov 26, 2026
First Nations leader Lesley Coulthard was concerned about the future of her community. Photo: Supplied
First Nations leader Lesley Coulthard was concerned about the future of her community. Photo: Supplied

Better Outback Group is raising concerns around future plans for the Davenport-Neuroodla-Leigh Creek transmission line after its owner and operator, ElectraNet, said it was reaching the “end of its service life”.

“A 240-kilometre line does not fail evenly along its length, and the public is entitled to see what it would cost to strengthen the critical towers, rebuild the worst sections in stages, or permanently restore the Davenport-Neuroodla section on its own,” group spokesperson Nigel Carney said.

“Once you change the gauge of the number of lines stretched across towers, they’re under less wind shear, so you don’t have the maintenance and the storm damage issues.

“So, that option should be looked at, very simply, as an ongoing line, but a sensible downgrade so that it matches the capacity of the region.”

It comes as thousands of South Australians were temporarily left without power after a monstrous storm brought down transmission towers run by ElectraNet on the Eyre Peninsula.

Better Outback Group members, including First Nations leader Lesley Coulthard, believed the option of downgrading the line has not been explored properly, with Carney saying investment could increase the population of the struggling region.

“We’re struggling here employment-wise – everybody’s looking for jobs, and we’ve got young kids who are ready to leave school, and they don’t want to leave the area, and we all want employment this way,” Coulthard said.

Meanwhile, Carney said that the line was currently the only source of energy connection for Outback communities and harked back to the region’s coal mining history.

“We’re all going through extreme cost of living pressure here in the Outback – we have extreme fuel prices and incredible energy prices,” he said.

According to ElectraNet, the line is “characterised by non-consecutive structural design standards and ageing components” and, if not replaced, “the likelihood of asset failure will continue to increase”, which would lead to issues such as unplanned outages.

ElectraNet said the line currently serves “relatively low loads” of power to Leigh Creek and Neuroodla and is “increasingly vulnerable to the impacts of climate change and extreme weather due to the age and historic design standards”.

Three options are currently being considered for the 240-kilometre power line, which dates back to the 1960s and was originally used to supply energy to the Leigh Creek Coal Mine.

Stay informed, daily

The line has suffered weather damage over the past 15 years, with an incident in October 2024 resulting in damage to 18 structures across two sections.

Options being considered for the line include replacing the entire line, which would cost $300 million to build, plus $29 million to decommission the old line and ongoing maintenance costs of $1.6 million each year.

A second option would see the entire line decommissioned, and a stand-alone power system (SAPS) established at Leigh Creek and Neuroodla, costing $52 million to establish plus decommissioning and ongoing maintenance costs.

SAPS refers to a local electricity system that is not physically connected to the main electricity network, which includes local generation, battery storage and back-up generation.

A third option would replace the section of the line running from Davenport to Neuroodla for $100 million, while a SAPS would be established at Leigh Creek and the remainder of the line would be decommissioned.

ElectraNet said the preferred option would be for the line to be decommissioned and a permanent SAPS established at Leigh Creek and Neuroodla. Despite requiring legislative change, ElectraNet is confident it could make this option work.

Currently, the only legal option for ElectraNet would be to replace the entire line for $300 million dollars.

Other options considered by ElectraNet but not progressed include refurbishing the existing line, establishing SAPS supply for Leigh Creek and Neuroodla and de-energising the transmission line to keep it in a care-and-maintenance state, and retaining the transmission line with permanent network support.

According to ElectraNet, while refurbishment is “technically feasible”, it was “expected to be of similar or higher cost than full replacement, requires prolonged construction in difficult access conditions, and would require generation/network support during works to maintain supply and reliability compliance”.

Carney believed the line would be better managed by the government, calling the privatisation of the Electricity Trust of South Australia “part of the shuffling of chairs” with assets.

“Playford created public ownership in South Australia, which caused the most fantastic period of economic expansion and growth. So, it’s a sensible thing to look at what can be done so that the public come first,” he said.