Costs linked to the new MotoGP race are now around $150 million but the Premier says a new pit building used for the bp Adelaide Grand Final needed replacing.

Premier Peter Malinauskas says the state government is buying a new $36 million pit building for the upcoming bp Adelaide Grand Final and MotoGP races.
He said this was expected to reduce construction and pack-away times in the Adelaide Park Lands by up to a third, leading to fewer road closures and disruptions.
It would replace the existing 18-year-old structure that Malinauskas said was past its use-by date.
The new structure has 37 pit garages, and it will be fully compliant with Fédération Internationale de Motocyclisme (FIM) and Fédération Internationale de l’Automobile (FIA) standards.
The new building will be delivered by Losberger De Boer Australia and will be used for the inaugural MotoGP event in November next year.
Malinauskas said today that the bp Adelaide Grand Final on the weekend was a great success with 262,000 people attending across four days.
He told ABC Radio this morning that in terms of economic benefits for the Adelaide Grand Final and MotoGP “we will get at least a $200 million benefit as a result of these two events combined” with the pit building to be used by both events.
Work would now be starting in earnest on December 6 to build the new $96 million MotoGP track, with the Premier saying that construction would be cleared away from the corner of the East End that is home to the Fringe Festival from February 19 to March 21.
The Adelaide Fringe is the biggest open access festival in the southern hemisphere and costs $35 million to stage annually; 13 per cent of the funding comes from state government.
The remainder comes through partnerships, ticketing fees, registrations and other business activity, as well as the Adelaide Fringe Foundation.
Adelaide Fringe delivered about $238.3 million to state coffers in 2026, Arts Minister Kyam Maher said earlier this year.
More than six million people attended ticketed and free Fringe events, with the festival again exceeding its million-ticket milestone, selling about 1,083,000 tickets – the equivalent of filling Adelaide Oval more than 20 times.
In terms of the new MotoGP track being built, another $15 million had already been announced for a Nature Positive Package, with the government also announcing on the weekend that it would preserve 94 olive trees earlier identified for removal for the Adelaide Circuit Redevelopment Project.
The change means the number of trees to be removed in the Adelaide Park Lands has been reduced to 288, with the trees removed from King Rodney Park being transplanted in the park lands.
The South Australian Government has said it would replace every removed tree on a 10:1 basis. All replacement trees will be mature stock, ranging from 45 litres to 200 litres. There will also be 123,000 new understorey plantings.
Malinauskas said the government worked “with council to deliver the upgrade of the Adelaide Street Circuit while seeing to an increase in tree canopy and biodiversity in the Adelaide Park Lands”.
“We’ve always said we’d minimise tree loss, and we’ve been working hard with arborists, the Adelaide City Council and others to ensure we do just that,” he said.
Adelaide Lord Mayor Jane Lomax-Smith thanked the Premier and state government for “working closely with the City of Adelaide to achieve this result”.
Works on the world’s first city street circuit ahead of the MotoGP™ Red Bull Grand Prix of Australia included: